Working Days determination
Whenever I encounter a production problem, I want to enter the problem in my access databse. I want to enter the investigation start date, product name, due date and problem description. I want the due date to automatically diplay a date after 30 working days from investigation date (No Saturadays and Sundays). How do I do that???????????
Thanks, Druach |
|
#2
|
|||
|
|||
|
One quick and cheap way, if you only want to exclude the weekends and aren't worried about holidays, the just add 42 days to you date (6 weeks)
S- |
![]() |